Software Project Management Questions & Answers | SPM | MCQ

Software Project Management Questions & Answers | SPM | MCQ

In this Software Project Management MCQ, we will cover topics such as Software Project Management, software management, software project, what is software project management, software program management, software project planning, construction software project management, agile software project management, online software project management, software project management tools, software project management online, software project, software program management, software project planning, software project development, project management in software engineering, project management software development, software projects and so on.

Question 1
Project has uncertainties on some functionalities at the beginning which will improve over time. Which software development model is suitable?
Select one:
a. None of the above
b. Waterfall
c. Iterative
d. Incremental


The Correct answer is: None of the above

Question 2
Object point method best suited for
Select one:
a. Designing
b. Testing
c. Coding
d. Estimation


The Correct answer is: Estimation

Question 3
This term is least critical from customer view point
Select one:
a. UAT
b. Unit testing
c. Delivery timeliness
d. Milestones


The Correct answer is: Milestones

Question 4
Following method is not used for project planning
Select one:
a. Activity Diagram
b. CPM
c. Timesheet
d. Gantt chart


The Correct answer is: Timesheet

Question 5
There are ________ types of Work Breakdown Structures.
Select one:
a. Four
b. Three
c. none
d. Two


The Correct answer is: Two

Question 6
If Task A to complete, it takes 10 days of human effort. It started 5 days earlier to the scheduled date and completed on 35th day. Then, the float value
Select one:
a. 25
b. 10
c. 20
d. 15
Question 7
Which of the following is not achieved by an automated estimation tools?
Select one:
a. Predicting clients demands.
b. Predicting software schedules.
c. Predicting software cost.
d. Predicting staffing levels.


The Correct answer is: Predicting clients demands.

Question 8
The Mangers use the acronym SMART while goal setting. What does SMART stand for?
Select one:
a. spectacular, measurable, actionable, resourced, timely
b. specific, measurable, achievable, relevant, timely
c. suitable, measurable, actionable, reviewed, timely
d. standardised, measurable, actionable, resourced, timely


The Correct answer is: specific, measurable, achievable, relevant, timely

Question 9
Which of these is NOT true for a matrix organizational structure?
Select one:
a. It follows the unity of command principle rigorously
b. Task and personality conflicts are a disadvantage of Matrix structure
c. Individual operators have to do double reporting both to a Project Manager and to the Functional manager
d. It is generally employed in project driven organizations


The Correct answer is: It follows the unity of command principle rigorously




Question 10
Arrange the following steps to form a basic/general Engineering Process Model.
1)Test
2)Design
3)Install
4)Specification
5)Manufacture
6)Maintain
Select one:
a. 4, 2, 5, 1, 3, 6
b. 2, 4, 5, 1, 3, 6
c. 4, 2, 5, 1, 6, 3
d. 2, 4, 5, 1, 6, 3

The Correct answer is: 4, 2, 5, 1, 3, 6

Question 11
Project management (PM) is the application of _________________ to meet project requirements.
Select one:
a. skills, tools and techniques
b. knowledge, skills, tools and techniques
c. knowledge, tools and techniques
d. knowledge, skills, tools


The Correct answer is: knowledge, skills, tools and techniques

Question 12
A ____ is the sequence of processing steps that completely handles one business transaction or customer request
Select one:
a. Model
b. Workflow
c. Prototype
d. Mock-up


The Correct answer is: Workflow

Question 13
______ model is not suitable for accommodating any change
Select one:
a. Waterfall Model
b. Prototyping Model
c. Build & Fix Model
d. RAD Model


The Correct answer is: Waterfall Model

Question 14
Smith is a project manager for ABC Video games. He has produced a project network diagram and has updated the activity list. Which process have he just finished?
Select one:
a. The Activity Sequencing process, which identifies all the activities dependences
b. The Activity Sequencing process, which identifies all the specific activities of the project
c. The activity duration Estimating process, which identifies all the dependent activities of the project
d. The activity duration Estimating process, which diagram project network time estimates


The Correct answer is: The Activity Sequencing process, which identifies all the specific activities of the project

Question 15
Which of the following costs is not part of the total effort cost?
Select one:
a. Costs of support staff
b. Costs of lunch time food
c. Costs of networking and communications
d. Costs of providing heating and lighting office space


The Correct answer is: Costs of lunch time food

Question 16
Which of the following is the process of assembling program components, data, and libraries, and then compiling and linking these to create an executable system?
Select one:
a. Change management
b. Version management
c. Release management
d. System building


The Correct answer is: System building

Question 17
Which of the following is a people-intensive activity?
Select one:
a. Project management
b. Organization
c. Motivation
d. Problem solving


The Correct answer is: Project management

Question 18
What are the signs that a software project is in trouble?
Select one:
a. Changes are managed poorly.
b. Deadlines are unrealistiC)
c. The product scope is poorly defineD)
d. All of the given options.


The Correct answer is: All of the given options.

Question 19
If a software production gets behind schedule, one can add more programmers and catch up.
Select one:
a. True
b. False


The Correct answer is: False




Question 20
The project life cycle consists of
Select one:
a. Objectives of the project
b. All of the above
c. Formulation and planning various activities
d. Understanding the scope of the project

The Correct answer is: All of the above

Question 21
Which of the following are parameters involved in computing the total cost of a software development project?
Select one:
a. All of the mentioned
b. Travel and training costs
c. Hardware and software costs
d. Effort costs


The Correct answer is: All of the mentioned

Question 22
An estimation technique ____________measure the size of the functionality to be developed.
Select one:
a. Analogy
b. Function Point
c. WBS


The Correct answer is: Function Point

Question 23
Which of the following is not generally considered a stakeholder in the software process?
Select one:
a. end users
b. project team
c. sales team
d. customer


The Correct answer is: sales team

Question 24
What is the simplest model of software development paradigm?
Select one:
a. Big Bang model
b. Spiral model
c. V-model
d. Waterfall model


The Correct answer is: Waterfall model

Question 25
The PERT technique gives most weightage to:
Select one:
a. the most pessimistic estimate obtained
b. the most optimistic estimate obtained
c. the most likely estimate obtained
d. all the estimates obtained have equal weights


The correct answer is: the most likely estimate obtained

Question 26
Which of the following is not a commonly used technique for schedule compression:
Select one:
a. quality reduction
b. use of overtime
c. scope reduction
d. resource reduction


The correct answer is: resource reduction

Question 27
To detect fraudulent usage of credit cards, the following data mining task should be used
Select one:
a. Outlier analysis
b. prediction
c. association analysis
d. feature selection


The correct answer is: Outlier analysis

Question 28
One of the best ways to avoid frustration during the software development process is to:
Select one:
a. Hide bad news from the project team members until things improve.
b. Give team members more control over process and technical decisions.
c. Give team members less control over process and technical decisions.
d. Reward programmers based on their productivity.


The Correct answer is: Give team members more control over process and technical decisions.

Question 29
Select from the following which is not project management goal
Select one:
a. Delivering the software to the customer at the agreed time.
b. Keeping overall costs within budget.
c. Maintaining a happy and well-functioning development team.
d. Avoiding costumer complaints.


The Correct answer is: Avoiding costumer complaints.

Question 30
Arrange the following steps to form a basic/general Engineering Process Model.
1. Test
2. Design
3. Install
4. Specification
5. Manufacture
6. Maintain
Select one:
a. 2, 4, 5, 1, 3, 6
b. 2, 4, 5, 1, 6, 3
c. 4, 2, 5, 1, 3, 6
d. 4, 2, 5, 1, 6, 3


The Correct answer is:4, 2, 5, 1, 3, 6

Question 31
—————— is the linear software development lifecycle methodology
Select one:
a. Prototyping
b. Spiral
c. Agile
d. Waterfall


The Correct answer is: Waterfall

Question 32
Which of the following is a reliability tactic?
A) improving individual components
B) increasing repair speed
C) providing redundancy
D) A and C
E) A, B, and C


Feedback
The correct answer is:A and C