Project Cost Management | PMP Quiz
PMP Quiz contain set of 10 MCQ questions for Project Cost Management MCQ which will help you to clear beginner level quiz.
- Reserve Analysis a technique NOT used in:
- Estimate Costs
- Determine Budget
- Control Costs
- Estimate Activity Duration
- A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000?
- Cost Variance
- Management Overhead
- Management Contingency Reserve
- Schedule Variance
- Project Cost Management Plan is created as a part of:
- Develop Project Management Plan process
- Estimate Costs process
- Determine Budget process
- Control Costs process
- A particular project in the domain of civil construction requires that every on-site worker be insured. Which of the following inputs BEST conveys this requirement to the Estimate Costs process so that the insurance cost is estimated and subsequently budgeted:
- Enterprise Environmental Factor
- Organizational Process Assets
- Project Scope Statement
- Project Management Plan
- _____________ is not a part of the project cost baseline but is included in the project budget:
- Activity Cost Contingency Reserve
- Management Contingency Reserve
- Management Overheads
- Project Management Planing
- _____________ is not part of the Earned Value calculations.
- Known Unknowns
- Unknown Unknowns
- Project Budget
- Amount of work completed
- What is the BEST way to make an accurate forecasting of ETC?
- Manual Forecasting of cost of remaining work.
- BAC – EV
- (BAC – EV)/CPI
- EAC – AC
- If the Earned Value is equal to Actual Cost, it means:
- Project is on budget and on schedule
- Schedule Variance Index is 1
- There is no schedule variance
- There is no cost variance
- Trend Analysis is BEST described as:
- Analyzing performance of similar projects over time
- Examining project performance over time
- Calculating Earned Value
- Calculating Cost Variance
- Which of the following is not done as part of Performance Measurements?
- Calculating Planned Value
- Calculating Earned Value
- Calculating ETC
- Calculating Cost Variance